B-193948, FEBRUARY 6, 1979

B-193948 Feb 06, 1979
Jump To:
Skip to Highlights

Highlights

DIGEST: REMISSION OF LIQUIDATED DAMAGES ASSESSED AGAINST CONTRACTOR WHO WAS NOT AT FAULT FOR LATE CONTRACT COMPLETION. IS APPROVED AS ADMINISTRATIVELY RECOMMENDED IN ACCORDANCE WITH PROVISIONS OF 10 U.S.C. 2312. INTEREST ON THE LIQUIDATED DAMAGES AMOUNT IS NOT PAYABLE. WERE ASSESSED AS A RESULT OF LATE COMPLETION OF CONTRACT F04609-77-90134. THE CLAIM FOR INTEREST IS NOT PAYABLE.

View Decision

B-193948, FEBRUARY 6, 1979

DIGEST: REMISSION OF LIQUIDATED DAMAGES ASSESSED AGAINST CONTRACTOR WHO WAS NOT AT FAULT FOR LATE CONTRACT COMPLETION, IS APPROVED AS ADMINISTRATIVELY RECOMMENDED IN ACCORDANCE WITH PROVISIONS OF 10 U.S.C. 2312. INTEREST ON THE LIQUIDATED DAMAGES AMOUNT IS NOT PAYABLE.

JOHN C. STETSON, SECRETARY OF THE AIR FORCE:

BY LETTER DATED JANUARY 11, 1979, WITH ATTACHMENTS, THE ASSISTANT SECRETARY (RESEARCH, DEVELOPMENT AND LOGISTICS) RECOMMENDED REMISSION OF LIQUIDATED DAMAGES ASSESSED AGAINST CLEMONS ELECTRICAL CONSTRUCTION. DAMAGES IN THE AMOUNT OF $1870, WERE ASSESSED AS A RESULT OF LATE COMPLETION OF CONTRACT F04609-77-90134.

BY VIRTUE OF THE AUTHORITY VESTED IN ME BY 10 U.S.C. 2312 AND IN ACCORDANCE WITH THE RECOMMENDATION OF THE ASSISTANT SECRETARY, I HEREBY APPROVE REMISSION OF THE LIQUIDATED DAMAGES IN THE AMOUNT OF $1870. THE CLAIM FOR INTEREST IS NOT PAYABLE.