Skip to main content

Protest Alleging Erroneous Bid Evaluation

B-192687 Published: Jun 05, 1979. Publicly Released: Jun 05, 1979.
Jump To:
Skip to Highlights

Highlights

A firm protested certain actions under an agency procurement alleging an erroneous bid evaluation. The agency invited bids to establish a Federal Supply Schedule for gas and electric domestic water heaters of various styles and capacities. The protest was denied because award evaluation may not be based on information furnished after bid prices are revealed when information differs from that submitted with the bid. Evaluation basis in the invitation for bids is controlling and the protesting bidder relied on contrary oral advice and past practices at its own risk.

Full Report

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries