Protest against Reasonableness of Government Hired Labor Estimate

B-189704 Published: Mar 29, 1978. Publicly Released: Mar 29, 1978.
Jump To:
Skip to Highlights

Highlights

A company, protesting the rejection of its bid on the basis of comparative costs with hired labor, argued that the Government's hired labor estimates were unreasonably low. The protester did not affirmatively prove that the Government's estimate was unreasonable, and the agency acted in accordance with statutes in rejecting the low bid which was more than 25 percent in excess of the revised estimated cost of performance by a Government plant.