Please note that a lapse in appropriations has caused GAO to shut down its operations. Therefore, GAO will not be able to publish reports or otherwise update this website until GAO resumes operations. In addition, the vast majority of GAO personnel are not permitted to work. Consequently, calls or emails to agency personnel may not be returned until GAO resumes operations. For details on how the bid protest process will be handled during the shutdown, please see the legal decisions page. For information related to the GAO Personnel Appeals Board (PAB), please see the PAB webpage.

Reconsideration of Decision Involving Possibility of Bid Errors

B-188946 May 30, 1978
Jump To:
Skip to Highlights

Highlights

The Forest Service requested reconsideration of a decision that dispelled allegations of a mistake in the bid and contended that the decision did not recognize the realities of timber bidding. Since the contracting officer was on notice concerning the possibility of a bid mistake and the bid was outside the range of the other bids received, the prior decision was affirmed.

Downloads

GAO Contacts

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries