Claim for Contract Price Increase because of Mistake in Bid
B-187556
Oct 22, 1976
Skip to Highlights
Highlights
A claim for a contract price increase because of a mistake in the bid is denied where the contractor, with knowledge of the mistake and without protest or reservation of the right to request an upward price adjustment, accepted award of the contract at the original bid price.