Please note that a lapse in appropriations has caused GAO to shut down its operations. Therefore, GAO will not be able to publish reports or otherwise update this website until GAO resumes operations. In addition, the vast majority of GAO personnel are not permitted to work. Consequently, calls or emails to agency personnel may not be returned until GAO resumes operations. For details on how the bid protest process will be handled during the shutdown, please see the legal decisions page. For information related to the GAO Personnel Appeals Board (PAB), please see the PAB webpage.

Bid Conditioned on Waiver of First Article Testing

B-185890 Jun 29, 1976
Jump To:
Skip to Highlights

Highlights

A company protested the rejection of its bid as nonresponsive because it qualified its bid on the waiver of first article testing. Since the bid was conditioned on the waiver, the ambiguity of the protester's bid rendered it nonresponsive. The waiver of the first article testing is a matter within the discretion of the agency and is not subject to questioning by GAO.

Downloads

GAO Contacts

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries