Protest against Agency's Decision To Exercise Contract Option
B-183098
Published: Feb 13, 1975. Publicly Released: Feb 13, 1975.
Skip to Highlights
Highlights
The contractor objected to the agency's exercise of a contract option, alleging that the option was exercised after the option period had expired. The allegation that the decision of the Government to exercise the option was in violation of the terms of the contract was a matter of contract administration and was not for consideration under GAO bid protest procedures.