Protest Alleging Erroneous Determination of Nonresponsibility
B-182967
Published: May 23, 1975. Publicly Released: May 23, 1975.
Skip to Highlights
Highlights
A firm objected to the rejection of its low bid, contending that the agency's determination of its nonresponsibility was erroneous. In the absence of a preaward survey, the contracting officer properly relied upon other recent preaward surveys and oral advice regarding the protester's current contract delinquencies in the determination of nonresponsibility. There was a reasonable basis for support of the agency's negative determination of responsibility.