Reconsideration of Sole-Source Procurement Denied
B-182248
Sep 25, 1975
Skip to Highlights
Highlights
A protester requested reconsideration of a decision involving a sole-source procurement, contending that it should have been allowed to compete for that procurement. The contracting officer acted properly in procuring on a sole-source basis, and since no material error of fact or law was established, the request for reconsideration was denied.
Downloads
GAO Contacts
Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel