B-167003, SEP 9, 1969

Skip to Highlights

Highlights

A CURRENT CONTRACTOR WHOSE CONTRACT WITH RENEWAL OPTION WAS NOT RENEWED MAY NOT HAVE SUCH FAILURE REGARDED AS CHANGE OF CONTRACT SINCE RENEWAL CLAUSE PROVIDED THAT GOVERNMENT MUST SERVE NOTICE OF DESIRE TO RENEW AND CONTRACTOR MUST AGREE IN WRITING. THEREFORE POSSIBILITY THAT THERE MIGHT NOT BE RENEWAL IS INHERENT IN CONTRACT. MARTIN: REFERENCE IS MADE TO YOUR LETTER OF AUGUST 13. WHICH HELD THAT THERE WERE DEFECTS IN THE NEGOTIATION PROCEDURES EMPLOYED UNDER FOREST SERVICE SOLICITATION R3-69-64. HAS PREVIOUSLY BEEN FURNISHED TO YOU AND THEREFORE WILL NOT BE REPEATED HERE. YOU STATE THAT YOU HAVE FURNISHED AIR TANKER SERVICES TO. HAVE HAD A GOOD WORKING RELATIONSHIP WITH. YOU INDICATE THE BASIS UPON WHICH YOU BELIEVE OFFERS SHOULD BE EVALUATED IF THERE IS TO BE FURTHER NEGOTIATION FOR THE SERVICES INVOLVED.

View Decision

GAO Contacts

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries