Department of Energy:
Accelerated Closure of Rocky Flats: Status and Obstacles
RCED-99-100: Published: Apr 30, 1999. Publicly Released: May 17, 1999.
Additional Materials:
- Full Report:
Contact:
(202) 512-6082
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
Pursuant to a congressional request, GAO reviewed the Department of Energy's (DOE) ability to close the Rocky Flats Environmental Technology Site by the end of 2006, focusing on: (1) DOE's plans for accelerating the site's closure and challenges that could impede closure; (2) the condition of the site at closure and the activities that will remain after closure; and (3) the costs of closing the site and the savings expected from accelerating its closure.
GAO noted that: (1) while DOE and the Kaiser-Hill Company have had some success in accelerating cleanup activities, it is questionable whether they can meet DOE's target date of 2006 for cleaning up and closing Rocky Flats at the costs and savings originally projected; (2) they face numerous challenges, significant compression of scheduled activities, and unresolved issues relating to the disposal of certain wastes and the site's condition at closure; (3) Kaiser-Hill has encountered delays in implementing its plan to close the site in 2010 and expects to have a detailed plan and schedule for closing the site by the end of 2006 in May 1999; (4) DOE and Kaiser-Hill believe that the contractor can take advantage of learning curves and efficiencies gained through early efforts to expedite cleanup and closure activities; (5) DOE and Kaiser-Hill must overcome various challenges to accelerate key activities to close the site by the end of 2006; (6) while plans for closing the site depend on other organizations within and outside DOE to take the site's materials and wastes for storage or disposal, several types of materials and wastes have no sites available to take them; (7) DOE and Kaiser-Hill officially maintain that the contractor can close the site by the end of 2006; (8) DOE, the Environmental Protection Agency (EPA), and Colorado have agreed on the condition of the site when it is closed; (9) nevertheless, many specific decisions still must be made; (10) if a more stringent cleanup level will be required than the interim level agreed to by DOE, EPA, and Colorado, the site's closure could be delayed; (11) developing plans and cost estimates for the site after closure will be difficult until agreement has been reached on all aspects of the site's closure and on future uses of the site; (12) the costs of cleaning up and closing Rocky Flats could be higher than DOE's official estimate; (13) although DOE has not validated the accuracy of the estimate, DOE and contractor site managers maintain that the site can be closed for $7.3 billion; (14) the contractor's 1998 detailed cost estimate, based on the costs of specific projects needed to close the site, totalled $8.4 billion; (15) these estimates do not include the costs that will be incurred after the site is closed; (16) the savings estimate for accelerating the site's closure from 2010 to 2006 was based on avoiding the costs of operating and maintaining the site for 4 years; and (17) if the cleanup and closure can be accelerated, health and safety risks may be reduced and financial benefits may be achieved.
Dec 10, 2020
-
Uranium Management:
Actions to Mitigate Risks to Domestic Supply Chain Could Be Better Planned and CoordinatedGAO-21-28: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 8, 2020
-
Offshore Wind Energy:
Planned Projects May Lead to Construction of New Vessels in the U.S., but Industry Has Made Few Decisions amid UncertaintiesGAO-21-153: Published: Dec 8, 2020. Publicly Released: Dec 8, 2020.
Nov 19, 2020
-
Nuclear Waste Disposal:
Better Planning Needed to Avoid Potential Disruptions at Waste Isolation Pilot PlantGAO-21-48: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Oct 29, 2020
-
Nuclear Safety:
DOE and the Safety Board Should Collaborate to Develop a Written Agreement to Enhance OversightGAO-21-141: Published: Oct 29, 2020. Publicly Released: Oct 29, 2020.
Oct 15, 2020
-
Nuclear Weapons:
NNSA Plans to Modernize Critical Depleted Uranium Capabilities and Improve Program ManagementGAO-21-16: Published: Oct 15, 2020. Publicly Released: Oct 15, 2020.
Jul 24, 2020
-
Nuclear Weapons:
Action Needed to Address the W80-4 Warhead Program's Schedule ConstraintsGAO-20-409: Published: Jul 24, 2020. Publicly Released: Jul 24, 2020.
Jun 24, 2020
-
National Nuclear Security Administration:
Analyzing Cost Savings Program Could Result in Wider Use and Additional Contractor EfficienciesGAO-20-451: Published: Jun 24, 2020. Publicly Released: Jun 24, 2020.
Jun 9, 2020
-
Nuclear Weapons:
NNSA Needs to Incorporate Additional Management Controls Over Its Microelectronics ActivitiesGAO-20-357: Published: Jun 9, 2020. Publicly Released: Jun 9, 2020.
May 13, 2020
-
Environmental Liabilities:
DOE Needs to Better Plan for Post-Cleanup Challenges Facing SitesGAO-20-373: Published: May 13, 2020. Publicly Released: May 13, 2020.
May 12, 2020
-
Hanford Waste Treatment Plant:
DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to RiseGAO-20-363: Published: May 12, 2020. Publicly Released: May 12, 2020.
Looking for more? Browse all our products here