Pursuant to a congressional request, GAO examined allegations concerning the development of fishways at three hydropower projects, specifically that: (1) the Department of the Interior Assistant Secretary for Fish and Wildlife and Parks overruled the Fish and Wildlife Service (FWS) regarding Federal Power Act requirements for the development of fishways at two projects; (2) the Assistant Secretary planned to approve the third project over FWS objections; (3) the Federal Energy Regulatory Commission (FERC) questioned the Secretary of the Interior's authority to prescribe fishways under the Federal Power Act; and (4) FERC officials prepared one or more draft letters for Interior's signature regarding the fishways issue, including the withdrawal of a motion to intervene in one case.

GAO found that: (1) Interior adequately provided for fishways at the three projects; (2) FERC acted within the scope of its authority with respect to the three projects; (3) FERC correctly acknowledged that it must require licensees to implement fishways requirements as Interior prescribes them; and (4) there was no indication that FERC intended to impede FWS activities.

Mar 20, 2018

Mar 14, 2018

Feb 28, 2018

Feb 16, 2018

Feb 6, 2018

Jan 30, 2018

Dec 7, 2017

Nov 14, 2017

Nov 1, 2017

Oct 26, 2017

Looking for more? Browse all our products here