Synthetic Fuels:
Status of the Great Plains Coal Gasification Project--August 1, 1985
RCED-86-36: Published: Dec 24, 1985. Publicly Released: Dec 24, 1985.
Additional Materials:
- Full Report:
Contact:
GAO reported on the status of the Great Plains Coal Gasification Project and the project sponsors' default on a $1.54 billion federally guaranteed loan.
GAO found that, although the Synthetic Fuels Corporation approved a loan agreement for up to $720 million in price guarantees over a 10-year period subject to restructuring the payments on a Department of Energy (DOE) guaranteed loan, DOE would not approve the proposed agreement because oil and natural gas prices were not high enough to make the project economical. However, GAO found that the project: (1) progressed well; (2) has met the production performance criteria for commercial operations; (3) was completed on time and within cost estimates; (4) has produced and sold $153 million worth of synthetic gas; (5) has had some technical problems; and (6) needs plant modifications to meet design specifications and environmental control standards.
Dec 10, 2020
-
Uranium Management:
Actions to Mitigate Risks to Domestic Supply Chain Could Be Better Planned and CoordinatedGAO-21-28: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Dec 8, 2020
-
Offshore Wind Energy:
Planned Projects May Lead to Construction of New Vessels in the U.S., but Industry Has Made Few Decisions amid UncertaintiesGAO-21-153: Published: Dec 8, 2020. Publicly Released: Dec 8, 2020.
Nov 19, 2020
-
Nuclear Waste Disposal:
Better Planning Needed to Avoid Potential Disruptions at Waste Isolation Pilot PlantGAO-21-48: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Oct 29, 2020
-
Nuclear Safety:
DOE and the Safety Board Should Collaborate to Develop a Written Agreement to Enhance OversightGAO-21-141: Published: Oct 29, 2020. Publicly Released: Oct 29, 2020.
Oct 15, 2020
-
Nuclear Weapons:
NNSA Plans to Modernize Critical Depleted Uranium Capabilities and Improve Program ManagementGAO-21-16: Published: Oct 15, 2020. Publicly Released: Oct 15, 2020.
Jul 24, 2020
-
Nuclear Weapons:
Action Needed to Address the W80-4 Warhead Program's Schedule ConstraintsGAO-20-409: Published: Jul 24, 2020. Publicly Released: Jul 24, 2020.
Jun 24, 2020
-
National Nuclear Security Administration:
Analyzing Cost Savings Program Could Result in Wider Use and Additional Contractor EfficienciesGAO-20-451: Published: Jun 24, 2020. Publicly Released: Jun 24, 2020.
Jun 9, 2020
-
Nuclear Weapons:
NNSA Needs to Incorporate Additional Management Controls Over Its Microelectronics ActivitiesGAO-20-357: Published: Jun 9, 2020. Publicly Released: Jun 9, 2020.
May 13, 2020
-
Environmental Liabilities:
DOE Needs to Better Plan for Post-Cleanup Challenges Facing SitesGAO-20-373: Published: May 13, 2020. Publicly Released: May 13, 2020.
May 12, 2020
-
Hanford Waste Treatment Plant:
DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to RiseGAO-20-363: Published: May 12, 2020. Publicly Released: May 12, 2020.
Looking for more? Browse all our products here