Implementation of the Bureau of Reclamation's Safety of Dams Program

RCED-86-139BR: Published: Apr 25, 1986. Publicly Released: May 6, 1986.

Additional Materials:


Office of Public Affairs
(202) 512-4800

Pursuant to a congressional request, GAO reviewed the Bureau of Reclamation's Safety Evaluation of Existing Dams Program to determine: (1) the number of dams with safety problems that the Bureau had identified; (2) the number of dams modified; and (3) the adequacy of funding to correct dams identified as needing safety modifications.

GAO found that the Bureau: (1) inspected all of the 275 dams in its safety program; (2) completed detailed safety analyses on 125 dams and has plans to complete analyses on the remaining dams by 1994; (3) corrected safety deficiencies at 13 dams at a cost of $31 million; and (4) identified 67 dams needing safety modifications. Bureau officials believe that the $750 million authorization should be sufficient to carry out the modifications; however, because all safety analyses have not been completed, the estimated costs cannot be refined. GAO believes that the program funds should not be used for the construction of a dam at the Central Arizona Project because this would leave a relatively smaller share for work at other facilities; therefore, the Bureau will have to reconsider its plans for and the use of those funds.

Mar 12, 2018

Feb 22, 2018

Jan 26, 2018

Jan 19, 2018

Jan 4, 2018

Dec 22, 2017

Dec 13, 2017

Nov 15, 2017

Nov 2, 2017

Oct 30, 2017

Looking for more? Browse all our products here