Nuclear Waste Disposal:

Better Planning Needed to Avoid Potential Disruptions at Waste Isolation Pilot Plant

GAO-21-48: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.

Additional Materials:

Contact:

Allison B. Bawden
(202) 512-3841
bawdena@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

The Waste Isolation Pilot Plant in New Mexico is the nation's only repository for certain waste from nuclear weapons research and production.

The facility is expected to run out of disposal space by 2025. The Department of Energy plans to expand it, but work may not be completed before existing space is full.

Accidents in 2014 reduced the plant's operations, and Energy is constructing a new ventilation system so that full operations can resume. This work has been delayed and the office managing it has many vacancies.

We recommended that Energy improve its planning for adding space and analyze what additional incentives could help fill vacancies.

Above-ground portion of the ventilation system at the Waste Isolation Pilot Plant in New Mexico

A series of gray-colored ventilation ducts situated above-ground.

Additional Materials:

Contact:

Allison B. Bawden
(202) 512-3841
bawdena@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

What GAO Found

The Department of Energy's (DOE) plans for the Waste Isolation Pilot Plant (WIPP) may ensure sufficient statutory capacity and physical space to meet its disposal needs for the defense-related transuranic (TRU) waste in its current inventory. To reduce the volumes counted against the statutory limit, DOE implemented a new counting method that excludes some of the air space found in certain waste packages (see fig.). The new method has been approved by the New Mexico state regulator. However, DOE may not have sufficient statutory capacity and physical space to meet future TRU waste disposal needs at WIPP if significant volumes of TRU waste are added to DOE's TRU waste inventory, as anticipated, or if the new counting method is successfully challenged in court.

Old and New Volume Counting Methods for Certain Waste Containers Disposed of in the Waste Isolation Pilot Plant

Old and New Volume Counting Methods for Certain Waste Containers Disposed of in the Waste Isolation Pilot Plant

DOE officials identified two challenges to completing key ventilation projects needed to return WIPP to full disposal operations: (1) overseeing contractors executing the projects and (2) obtaining regulatory approvals. According to the workforce plan for DOE's Carlsbad Field Office, it may not have sufficient staff to address these challenges. The Carlsbad Field Office is responsible for project oversight, among other things, and 27 of the office's 76 total positions were either vacant or occupied by acting officials as of January 2020. DOE has taken some steps to address these staffing shortages; however, DOE has not fully analyzed options to address the vacancy issue. By doing so, DOE will be in a better position to address the challenges it has identified to effectively completing the projects at WIPP.

DOE does not have assurance that WIPP's planned additional physical space will be constructed before existing space is full, which would result in a potential interruption to disposal operations. GAO assessed DOE's Integrated Master Schedule—which includes DOE's estimate for completing some of WIPP's additional physical space—against best practices for schedule estimating. GAO found that the schedule did not substantially meet all four characteristics of a reliable schedule; to be considered reliable, a schedule must at least substantially meet all four. By improving the schedule, DOE will have greater assurance in the reliability of its estimate for completing additional physical space before existing space is full, thereby avoiding interruptions to disposal operations.

Why GAO Did This Study

DOE's WIPP is the nation's only deep geologic repository for the disposal of defense-related nuclear waste. DOE suspended operations at WIPP after two accidents in 2014 and resumed on a limited scale in 2017. DOE has initiated two projects to improve WIPP's underground ventilation system and allow full disposal operations to resume. However, DOE estimates WIPP's existing physical space will be full around 2025, and DOE faces a statutory limitation on how much waste can be disposed of at WIPP.

Senate Report No. 115-125 accompanying a bill for the National Defense Authorization Act for Fiscal Year 2018 includes a provision for GAO to review DOE's actions to bring WIPP towards full operational status. This report examines DOE's (1) plans to meet needs for physical space at WIPP without exceeding WIPP's statutory capacity, (2) challenges to completing key ventilation projects, and (3) plans for adding physical space at WIPP without interruption to operations.

GAO reviewed DOE documents for project designs, compared schedules to best practices, and interviewed DOE officials at the Carlsbad Field Office.

What GAO Recommends

GAO is making three recommendations, including that DOE analyze options to address staffing vacancies and improve its schedule for adding physical space at WIPP. DOE agreed with all three recommendations.

For more information, contact Allison B. Bawden at (202) 512-3841 or bawdena@gao.gov.

Recommendations for Executive Action

  1. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Assistant Secretary for Environmental Management should identify and fully analyze what additional flexibilities could be used to address the staffing vacancies at CBFO. (Recommendation 1)

    Agency Affected: Department of Energy

  2. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Assistant Secretary for Environmental Management should ensure that the WIPP Integrated Master Schedule is updated so that it sufficiently follows best practices to at least substantially meet the four characteristics of a reliable schedule. (Recommendation 2)

    Agency Affected: Department of Energy

  3. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Assistant Secretary for Environmental Management should develop a plan for mitigating the potential impacts of the risks to DOE's TRU waste cleanup program posed by a potential interruption to waste disposal operations at WIPP. (Recommendation 3)

    Agency Affected: Department of Energy

 

Explore the full database of GAO's Open Recommendations »

Oct 29, 2020

Oct 15, 2020

Jul 24, 2020

Jun 24, 2020

Jun 9, 2020

May 13, 2020

May 12, 2020

Apr 29, 2020

  • energy icon, source: Art Explosion

    Priority Open Recommendations:

    Department of Energy
    GAO-20-285PR: Published: Apr 22, 2020. Publicly Released: Apr 29, 2020.

Apr 17, 2020

Mar 11, 2020

Looking for more? Browse all our products here