Uranium Management:
Actions to Mitigate Risks to Domestic Supply Chain Could Be Better Planned and Coordinated
GAO-21-28: Published: Dec 10, 2020. Publicly Released: Dec 10, 2020.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-3821
bawdena@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
The National Nuclear Security Administration relies on the commercial uranium industry to produce uranium for nuclear weapons and other national security missions. Under international agreements such uranium must be mined in the U.S. and enriched using U.S. technology. However, the U.S. has not had the capability to produce such uranium since 2013.
The U.S. released a new national strategy to address the concerns expressed by domestic uranium industry and support new uranium production. However, the strategy could be improved—for instance, by identifying the resources needed to carry it out. We recommended strategy improvements and more.
Idle Domestic Plant for Converting Uranium to a Form Suitable for Enrichment
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-3821
bawdena@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
Federal agencies, including the Department of Energy (DOE) and the separately organized National Nuclear Security Administration (NNSA) within DOE, and uranium industry representatives have identified risks to the commercial supply chain for uranium needed for defense purposes. Such uranium may need to be mined domestically and enriched using U.S. technology to be free of obligations for the peaceful use of uranium and certain technology imported under international agreements. Identified risks to the unobligated uranium supply chain include (1) possible loss of domestic uranium mining capabilities and (2) possible challenges in re-starting the only facility in the United States for converting natural uranium into a form suitable for use in enrichment operations. Further, the U.S. has not had an operating enrichment capability that uses U.S. technology since 2013.
Idle Domestic Plant for Converting Uranium to a Form Suitable for Enrichment
DOE and NNSA have initiated actions officials believe will mitigate such risks to the unobligated uranium supply chain. For example, DOE and NNSA have both taken steps to reestablish a domestic enrichment capability with U.S. technology. In addition, DOE has proposed creation of a domestic uranium reserve to help support the domestic uranium mining and conversion industries until market conditions improve. DOE's fiscal year 2021 budget request includes $150 million for the reserve. However, we cannot conclude that the estimate is reasonable because it is unclear how the funding needs for the reserve were determined. By providing a more complete analysis to support future funding requests for the reserve, DOE could better provide assurance that such requests would achieve objectives.
The Nuclear Fuel Working Group's strategy to mitigate risks to the domestic uranium industry does not fully incorporate all desirable characteristics GAO has identified for a national strategy. For example, it does not identify (1) the level of resources needed to support proposed actions or (2) an interagency coordinating mechanism. DOE is developing an implementation plan for the strategy, but DOE officials provided conflicting statements about the extent to which the agency will coordinate interagency implementation.
Why GAO Did This Study
NNSA has several defense needs for enriched uranium, including low-enriched uranium to produce tritium for nuclear weapons. To meet these needs, NNSA relies on commercial sectors of the domestic uranium industry, such as uranium mining or enrichment, which make up a supply chain for unobligated uranium. However, this industry faces commercial viability risks. In April 2020, the President's Nuclear Fuel Working Group released a strategy to mitigate risks to the domestic uranium industry. This working group includes DOE, the Department of Defense, and other agencies.
Senate Report 115-262 included a provision that GAO review NNSA's planning for the future supply of unobligated enriched uranium. This report examines (1) risks agencies and others have identified to the unobligated uranium supply chain and agency actions to mitigate those risks, and (2) the extent to which the Nuclear Fuel Working Group's risk mitigation strategy incorporates desirable characteristics of a national strategy. GAO analyzed key NNSA and DOE planning documents and interviewed NNSA and other agency officials and industry representatives.
What GAO Recommends
GAO is making three recommendations, including that DOE improve its cost estimate to support future funding requests for the proposed uranium reserve and ensure its implementation plan for the strategy addresses each of the desirable characteristics of a national strategy. DOE concurred with GAO's recommendations.
For more information, contact at (202) 512-3821 or bawdena@gao.gov.
Recommendations for Executive Action
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: The Secretary of Energy should ensure, particularly as operational details for the uranium reserve are clarified, that any future funding requests for the uranium reserve are based on cost estimates that have been thoroughly reviewed and deemed reasonable. (Recommendation 1)
Agency Affected: Department of Energy
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: The Director of NNSA's Office of Cost Estimating and Program Evaluation should, during the office's required review of NNSA's analysis of alternatives (AOA) for a capability to meet NNSA's future unobligated enriched uranium needs, ensure that the AOA was unbiased toward any solution. (Recommendation 2)
Agency Affected: Department of Energy: National Nuclear Security Administration: Office of Cost Estimating and Program Evaluation
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: The Secretary of Energy should ensure that the implementation plan under development for Restoring America's Competitive Nuclear Energy Advantage: a Strategy to Assure U.S. National Security fully addresses each of the desirable characteristics GAO has identified for a national strategy. (Recommendation 3)
Agency Affected: Department of Energy
Explore the full database of GAO's Open Recommendations
»
Dec 8, 2020
-
Offshore Wind Energy:
Planned Projects May Lead to Construction of New Vessels in the U.S., but Industry Has Made Few Decisions amid UncertaintiesGAO-21-153: Published: Dec 8, 2020. Publicly Released: Dec 8, 2020.
Nov 19, 2020
-
Nuclear Waste Disposal:
Better Planning Needed to Avoid Potential Disruptions at Waste Isolation Pilot PlantGAO-21-48: Published: Nov 19, 2020. Publicly Released: Nov 19, 2020.
Oct 29, 2020
-
Nuclear Safety:
DOE and the Safety Board Should Collaborate to Develop a Written Agreement to Enhance OversightGAO-21-141: Published: Oct 29, 2020. Publicly Released: Oct 29, 2020.
Oct 15, 2020
-
Nuclear Weapons:
NNSA Plans to Modernize Critical Depleted Uranium Capabilities and Improve Program ManagementGAO-21-16: Published: Oct 15, 2020. Publicly Released: Oct 15, 2020.
Jul 24, 2020
-
Nuclear Weapons:
Action Needed to Address the W80-4 Warhead Program's Schedule ConstraintsGAO-20-409: Published: Jul 24, 2020. Publicly Released: Jul 24, 2020.
Jun 24, 2020
-
National Nuclear Security Administration:
Analyzing Cost Savings Program Could Result in Wider Use and Additional Contractor EfficienciesGAO-20-451: Published: Jun 24, 2020. Publicly Released: Jun 24, 2020.
Jun 9, 2020
-
Nuclear Weapons:
NNSA Needs to Incorporate Additional Management Controls Over Its Microelectronics ActivitiesGAO-20-357: Published: Jun 9, 2020. Publicly Released: Jun 9, 2020.
May 13, 2020
-
Environmental Liabilities:
DOE Needs to Better Plan for Post-Cleanup Challenges Facing SitesGAO-20-373: Published: May 13, 2020. Publicly Released: May 13, 2020.
May 12, 2020
-
Hanford Waste Treatment Plant:
DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to RiseGAO-20-363: Published: May 12, 2020. Publicly Released: May 12, 2020.
Apr 29, 2020
-
Priority Open Recommendations:
Department of EnergyGAO-20-285PR: Published: Apr 22, 2020. Publicly Released: Apr 29, 2020.
Looking for more? Browse all our products here