Job Corps:
Actions Needed to Improve Planning for Center Operation Contracts
GAO-19-326: Published: Aug 8, 2019. Publicly Released: Sep 9, 2019.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-7215
brownbarnesc@gao.gov
Timothy J. DiNapoli
(202) 512-4841
dinapolit@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
The Department of Labor’s Job Corps program helps low-income youth obtain various skills, including those needed to find a job. Its centers are operated mostly by contractors.
We reviewed Labor’s use of bridge contracts at these centers. Such contracts can prevent a lapse in service after a contract ends. However, in certain circumstances, they may increase the risk of the government overpaying. We found that 68 contractor-run centers operated under bridge contracts during program year 2016 (July 1 to June 30), but use of bridge contracts decreased substantially the next year.
We recommended Labor better plan for awarding center contracts.
Job Corps Centers, February 2019

Map showing locations throughout the contiguous United States, Alaska, Hawaii, and Puerto Rico
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-7215
brownbarnesc@gao.gov
Timothy J. DiNapoli
(202) 512-4841
dinapolit@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
In program year 2016, the Department of Labor's (DOL) Employment and Training Administration (ETA) operated 68 of its 97 Job Corps centers using bridge contracts. GAO has generally defined a bridge contract as an extension to an existing contract or a new noncompetitive contract awarded to the current contractor to avoid a lapse in service. GAO found that ETA operated most of these Job Corps centers (49 of 68) under bridge contracts for at least a year, with over a third operating under bridges for 2 years or potentially longer. ETA cited workforce challenges such as staff vacancies and the need to address issues raised in protests as contributing to its use of bridge contracts.
ETA officials said they used various strategies to decrease their use of noncompetitive bridge contracts, including prioritizing efforts to award more contracts competitively. By the end of program year 2017, most of the centers operating under bridge contracts during program year 2016 (48 of 68) had transitioned to competitive contracts. Despite these efforts, ETA continues to face workforce challenges. Contracting officials expressed concern about having sufficient staff to award a large group of contracts that will begin to expire in program years 2021 and 2022 (see figure). ETA officials said it takes about 8 to 12 months from solicitation to contract award for new 5-year competitive procurements. Therefore, acquisition planning for a center contract set to expire in January 2021 would usually need to begin early 2020. However, ETA does not have a comprehensive workforce strategy to address its workforce challenges or support these new contract awards. As a result, ETA risks relying on noncompetitive bridge contracts again in the future.
The Number of Job Corps Centers GAO Projected to Need New Contracts in Program Years 2019-2023

Note: Centers are operated on a program year basis, which runs from July 1 of a given year to June 30 of the following year.
ETA used various strategies to monitor and incentivize contractor performance at the 10 centers GAO reviewed, including conducting onsite visits to Job Corps centers and paying incentive fees to contractors. However, contracting and program officials GAO interviewed had limited or no insight into how ETA calculates and pays incentive fees. Without coordinating and documenting the process for calculating incentive fees, ETA's program and contract officials may lack key information regarding contractor performance.
Why GAO Did This Study
Job Corps' 119 centers, which are operated primarily by contractors, provide an array of services to help low-income youth find a job, go to college, or enter the military. ETA is generally required to award competitive contracts, but can award noncompetitive contracts in certain instances. Some noncompetitive contracts act as bridge contracts—which can be a useful tool to avoid a lapse in service but, when used frequently and for prolonged periods, can increase the risk of the government overpaying for services.
This report examines (1) the extent to which ETA used bridge contracts to operate Job Corps centers in program year 2016; (2) strategies ETA used to decrease the use of noncompetitive bridge contracts; and (3) how ETA monitored contractor performance at selected Job Corps centers. GAO analyzed data from program years 2016 and 2017(the most current data available at the time we began our review) from the Federal Procurement Data System-Next Generation, and reviewed contract documents. GAO also conducted an in-depth review of 10 centers that reflected a mix of contractor performances and at least one center from Job Corps' six regions, and interviewed ETA officials.
What GAO Recommends
GAO is making two recommendations, including that ETA develop (1) a comprehensive strategy to account for workforce needs and future center contracts, and (2) a coordinated and documented process for sharing information on incentive fees paid to contractors. DOL agreed with GAO's recommendations.
For more information, contact Cindy S. Brown Barnes at (202) 512-7215 or brownbarnesc@gao.gov, or Timothy J. DiNapoli at (202) 512-4841 or dinapolit@gao.gov.
Recommendations for Executive Action
Status: Open

Comments: DOL stated that it will develop, document, and implement a comprehensive strategy that accounts for Job Corps' projected workload requirements and considers its acquisition workforce needs. DOL noted that it has released a new procurement plan which reflects its decision to re-procure 28 Job Corps centers prior to the final option year of their contract. DOL said that this action would result in each region having no more than five procurements each year, which it considers a manageable procurement workload for its current staffing level. We will consider closing the recommendation when such a comprehensive strategy is implemented.
Recommendation: The Assistant Secretary of ETA should develop, document, and implement a comprehensive strategy that (1) accounts for Job Corps' projected workload requirements and (2) considers its acquisition workforce needsincluding the number of staff, skills, and other supports necessary to plan, award, and monitor Job Corps center contractsto enable it to effectively plan for and competitively award future Job Corps center contracts. (Recommendation 1)
Agency Affected: Department of Labor: Employment and Training Administration
Status: Closed - Implemented

Comments: ETA developed a desk reference guide to provide regional staff with information on how incentive fees are calculated for Job Corps contractors. In addition, ETA national and regional staff hold biweekly meetings to discuss, among other topics, the status of contracts and expectations regarding the reconciliation process.
Recommendation: The Assistant Secretary of ETA should develop a coordinated and documented internal process to share relevant information on incentive fees paid to contractors with staff in its key offices. (Recommendation 2)
Agency Affected: Department of Labor: Employment and Training Administration
Explore the full database of GAO's Open Recommendations
»
Oct 19, 2020
-
Fair Labor Standards Act:
Observations on the Effects of the Home Care RuleGAO-21-72: Published: Oct 19, 2020. Publicly Released: Oct 19, 2020.
Jun 22, 2020
-
Workforce Innovation and Opportunity Act:
Additional DOL Actions Needed to Help States and Employers Address Substance Use DisorderGAO-20-337: Published: May 21, 2020. Publicly Released: Jun 22, 2020.
Apr 14, 2020
-
Job Corps:
DOL Should Provide Greater Transparency in Communicating Its Rationale for Closure DecisionsGAO-20-240R: Published: Apr 14, 2020. Publicly Released: Apr 14, 2020.
Feb 14, 2020
-
National Mediation Board:
Additional Actions Needed to Fully Implement Prior GAO Recommendations and Improve Agency Management and OversightGAO-20-236: Published: Feb 14, 2020. Publicly Released: Feb 14, 2020.
Feb 10, 2020
-
National Weather Service:
Information on Contractor Selection and Work Performed for Its Operations and Workforce Analysis ProjectGAO-20-271R: Published: Jan 30, 2020. Publicly Released: Feb 10, 2020.
Apr 10, 2019
-
Priority Open Recommendations:
Department of LaborGAO-19-395SP: Published: Apr 3, 2019. Publicly Released: Apr 10, 2019.
Apr 9, 2019
-
Military Spouse Employment:
Participation in and Efforts to Promote the My Career Advancement Account ProgramGAO-19-320R: Published: Apr 9, 2019. Publicly Released: Apr 9, 2019.
Apr 8, 2019
-
Workforce Automation:
Better Data Needed to Assess and Plan for Effects of Advanced Technologies on JobsGAO-19-257: Published: Mar 7, 2019. Publicly Released: Apr 8, 2019.
Mar 28, 2019
-
Employment and Training Programs:
Department of Labor Should Assess Efforts to Coordinate Services Across ProgramsGAO-19-200: Published: Mar 28, 2019. Publicly Released: Mar 28, 2019.
Feb 28, 2019
-
Contingent Workforce:
BLS is Reassessing Measurement of Nontraditional WorkersGAO-19-273R: Published: Jan 29, 2019. Publicly Released: Feb 28, 2019.
Looking for more? Browse all our products here


Explore our Key Issues on Employment