Nuclear Regulatory Commission:
Natural Hazard Assessments Could Be More Risk-Informed
GAO-12-465: Published: Apr 26, 2012. Publicly Released: May 29, 2012.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Text:
Contact:
(202) 512-3841
ruscof@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
The Nuclear Regulatory Commission (NRC) and companies licensed to operate nuclear power reactors (or licensees) apply probabilistic risk assessment (PRA) to natural hazards at operating U.S. nuclear reactors to a limited extent. When the 104 operating reactors were originally licensed before 1997, NRC required licensees to assess natural hazards using deterministic analysis, which—informed by historical experience, test results, and expert judgment—considers a specific set of potential accidents and how the consequences of those accidents can be prevented and mitigated. Subsequent to most of these initial licenses being issued, NRC, through policy statements and other documents, has endorsed PRA—a systematic method for assessing what can go wrong, its likelihood, and its consequences, resulting in quantitative estimates of risk—as a means to enhance and extend traditional deterministic analysis. In 1991, NRC requested that licensees voluntarily examine their reactors’ vulnerability to natural hazards and suggested PRA as one of several possible methods for licensees to use in their examinations. However, most licensees opted to use other methods. According to NRC officials and nuclear power industry representatives—and reflected in data GAO obtained from five licensees that together operate 25 reactors—few licensees are likely to have developed or updated since the 1990s PRAs that address natural hazards. NRC would have to conduct an analysis to determine whether or not to require licensees to develop PRAs that address natural hazards. According to agency officials, NRC has not conducted such an analysis.
The experts in assessing natural hazards and/or nuclear reactor risks that GAO interviewed offered a range of views on (1) the overall adequacy of NRC processes for assessing the threats that natural hazards pose to operating U.S. nuclear power reactors and (2) what, if any, changes to those processes are warranted. Several experts said they believe NRC processes are generally adequate for assessing the threats that natural hazards pose to operating reactors. However, more than half of the experts GAO interviewed suggested expanding the use of PRA for assessing natural hazards as a complement to traditional deterministic analyses to provide a more robust approach. Those experts cited a number of advantages to doing so, including that PRA can help identify vulnerabilities that might otherwise be overlooked by relying on traditional deterministic analyses alone. Several experts also identified challenges to expanding the use of PRA for assessing natural hazards, including the limited number of experts qualified to develop PRAs and the costs of doing so.
Why GAO Did This Study
On March 11, 2011, an earthquake triggered a tsunami wave that exceeded the seawall at Japan’s Fukushima Daiichi nuclear power plant, leading to the release of radioactive material into the environment. The disaster raised questions about the threats that natural hazards, such as earthquakes and floods, may pose to U.S. commercial nuclear power reactors. NRC licenses and regulates U.S. nuclear power reactors. NRC criteria for licensees to assess natural hazards were developed using an approach that required reactors to be designed according to a set of potential accidents using deterministic analysis. Since the 1990s, NRC has been encouraging the use of PRA as part of a risk-informed, performance-based approach.
GAO was asked to (1) determine the extent to which PRA is applied to natural hazards at operating U.S. reactors and (2) describe expert views on and suggested changes, if any, to NRC processes for assessing natural hazards at such reactors. GAO reviewed documents; analyzed responses from 15 experts in assessing nuclear reactor risks and/or natural hazards; visited five selected nuclear power plants; and interviewed NRC officials and industry and public interest group representatives.
What GAO Recommends
GAO recommends that NRC analyze whether licensees of operating reactors should be required to develop PRAs that address natural hazards. NRC agreed with the recommendation and stated it will conduct the analysis in the context of ongoing initiatives.
For more information, contact Frank Rusco at (202) 512-3841 or ruscof@gao.gov.
Recommendation for Executive Action
Status: Closed - Implemented

Comments: In April 2012, we reported that the Nuclear Regulatory Commission (NRC) had endorsed probabilistic risk assessment (PRA) as a means to enhance and extend traditional deterministic assessments, but the agency had not conducted the analyses to determine whether or not it should require licensees of operating reactors to develop and maintain PRAs that address natural hazards. NRC therefore did not have a strong basis to judge whether or not such a requirement should be implemented. We recommended that the NRC Commissioners direct agency staff to conduct and document any needed analyses to determine whether the agency should require licensees of operating reactors to develop and maintain PRAs that address natural hazards. Based in part on our work, the NRC staff evaluated the possibility of requiring all licensees of operating reactors to have plant-specific PRAs (which would address natural hazards) and documented the results of their evaluation in a December 2015 paper to the Commission. In that paper, the NRC staff concluded that NRC should not require licensees of operating reactors to have plant-specific PRAs because the substantial resource burden that the requirement would impose on licensees was not likely to be justified by its benefits. The Commission concurred with the NRC staff's paper in March 2016.
Recommendation: To improve safety decision making by the NRC in carrying out its responsibility under the Atomic Energy Act to ensure that the operation of nuclear power plants is consistent with the common defense and security and public health and safety, the NRC Commissioners should direct agency staff to conduct and document any needed analyses to determine whether the agency should require licensees of operating reactors to develop and maintain PRAs that address natural hazards.
Agency Affected: Nuclear Regulatory Commission
Explore the full database of GAO's Open Recommendations
»
Oct 15, 2020
-
Nuclear Weapons:
NNSA Plans to Modernize Critical Depleted Uranium Capabilities and Improve Program ManagementGAO-21-16: Published: Oct 15, 2020. Publicly Released: Oct 15, 2020.
Jul 24, 2020
-
Nuclear Weapons:
Action Needed to Address the W80-4 Warhead Program's Schedule ConstraintsGAO-20-409: Published: Jul 24, 2020. Publicly Released: Jul 24, 2020.
Jun 24, 2020
-
National Nuclear Security Administration:
Analyzing Cost Savings Program Could Result in Wider Use and Additional Contractor EfficienciesGAO-20-451: Published: Jun 24, 2020. Publicly Released: Jun 24, 2020.
Jun 9, 2020
-
Nuclear Weapons:
NNSA Needs to Incorporate Additional Management Controls Over Its Microelectronics ActivitiesGAO-20-357: Published: Jun 9, 2020. Publicly Released: Jun 9, 2020.
May 13, 2020
-
Environmental Liabilities:
DOE Needs to Better Plan for Post-Cleanup Challenges Facing SitesGAO-20-373: Published: May 13, 2020. Publicly Released: May 13, 2020.
May 12, 2020
-
Hanford Waste Treatment Plant:
DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to RiseGAO-20-363: Published: May 12, 2020. Publicly Released: May 12, 2020.
Apr 29, 2020
-
Priority Open Recommendations:
Department of EnergyGAO-20-285PR: Published: Apr 22, 2020. Publicly Released: Apr 29, 2020.
Apr 17, 2020
-
Priority Open Recommendations:
Nuclear Regulatory CommissionGAO-20-286PR: Published: Apr 10, 2020. Publicly Released: Apr 17, 2020.
Mar 11, 2020
-
Modernizing the Nuclear Security Enterprise:
Uranium Processing Facility Is on Schedule and Budget, and NNSA Identified Additional Uranium Program CostsGAO-20-293: Published: Mar 11, 2020. Publicly Released: Mar 11, 2020.
Mar 4, 2020
-
Nuclear Regulatory Commission:
Fee-Setting, Billing, and Budgeting Processes Have Improved, but Additional Actions Could Enhance EffortsGAO-20-362: Published: Feb 28, 2020. Publicly Released: Mar 4, 2020.
Looking for more? Browse all our products here


Explore our Key Issues on Energy