Nuclear Waste:
DOE Should Reassess Whether the Bulk Vitrification Demonstration Project at Its Hanford Site Is Still Needed to Treat Radioactive Waste
GAO-07-762: Published: Jun 12, 2007. Publicly Released: Jun 12, 2007.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Text:
Contact:
(202) 512-6870
contact@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
The Department of Energy (DOE) is demonstrating a technology called bulk vitrification, in parallel with the Hanford waste treatment plant, to treat a portion of the radioactive waste stored in 177 tanks at its Hanford site in southeastern Washington state. DOE faces technical and management problems that have affected the original objectives to justify demonstrating the bulk vitrification technology. This report discusses the extent to which DOE (1) has managed the bulk vitrification demonstration project consistent with DOE management guidance and (2) continues to need a supplemental technology, such as bulk vitrification, to treat a portion of the low-activity tank waste. To assess DOE's management of the project, GAO reviewed reports by DOE and others and discussed the project with DOE and contractor officials.
DOE did not follow its management requirements during the first 2 years of the demonstration project in an effort to accelerate tank waste cleanup. This decision contributed to a nearly fourfold increase in estimated costs from $62 million to $230 million and a 6-year delay on the project. DOE did not conduct key internal and external reviews and did not fully develop or update key project planning documents as required. Without these management tools, DOE initially overlooked a number of technical and safety problems facing the project, such as uncertainties about the quality of the glass formed using the bulk vitrification technology and inadequate systems to shield radioactive material from workers and the environment. In late 2005, largely because of these problems, DOE began taking steps to implement its management requirements on the project. DOE's need for a supplemental technology to treat a portion of the low-activity tank waste at Hanford is no longer clear, but DOE does not plan to reassess the need for the project before completing the demonstration. Originally, DOE justified the bulk vitrification project as a relatively low-cost, rapidly deployable supplemental technology to assist the department to complete tank waste treatment at Hanford by 2028. However, none of the key components to this justification remains today. First, the price of a full-scale bulk vitrification facility has risen to $3 billion or more, about the same cost as adding a second low-activity waste treatment facility to the waste treatment plant. Second, the technology is no longer rapidly deployable because, as discussed above, the project faces at least a 6-year delay. Finally, it is now apparent that completing tank waste treatment at Hanford by 2028 is not possible under any reasonable scenario and that the waste treatment plant must operate for longer than DOE previously planned. This is significant since longer operating periods may reduce the need for a supplemental technology. Given the plant's estimated treatment capacity, more of the low-activity waste could be treated in the waste treatment plant facilities. Although DOE's management guidance specifies that when conditions have significantly changed DOE should reassess the mission need of a project, DOE does not intend to conduct this reassessment because DOE officials said they want more information about the technology. Proceeding with the demonstration project before reaffirming the need for the project increases the risk that DOE will spend an additional $137 million or more to develop a technology that may not be needed.
Matter for Congressional Consideration
Status: Closed - Implemented
Comments: The department withheld funding on the bulk vitrification project until it conducted a reassessment of the need for the project. The department's reassessment ultimately resulted in the project's cancellation. Accordingly, DOE cancelled further funding on the project beginning in FY 2009. (See relevant status explanations below for details.)
Matter: Congress may wish to consider withholding future funding for the demonstration until the department conducts and reports on a reassessment that clearly confirms the need for a supplemental technology at Hanford and bulk vitrification as a viable alternative for treating Hanford's low-activity waste.
Recommendations for Executive Action
Status: Closed - Implemented
Comments: DOE expanded the scope of an ongoing study, originally slated for release in June 2007 but delayed until November 2007 to address our recommendation. This study concluded that DOE should continue to pursue developing a supplemental technology to accelerate tank waste cleanup at Hanford but did not endorse bulk vitrification as the best option. DOE commissioned an external study of waste treatment plant operations, including supplemental technologies for low-activity waste. This external technical review, which was issued in November 2008, concluded that a bulk vitrification facility was not the best option for meeting the tank waste treatment schedule.
Recommendation: In light of major changes that have occurred on both the bulk vitrification demonstration and the waste treatment plant, which may affect the demonstration's costs, schedule, and mission justification, the Secretary of Energy should direct the Assistant Secretary for Environmental Management to reassess the need for a supplemental technology to treat a portion of Hanford's low-activity tank waste. The reassessment should clearly identify how a supplemental technology would complement and be integrated with waste treatment plant operations.
Agency Affected: Department of Energy
Status: Closed - Implemented
Comments: In response to our report, DOE reassessed the bulk vitrification demonstration project and other available technologies to treat low-activity waste at Hanford. DOE expanded the scope of an ongoing study, originally slated for release in June 2007 but delayed until November 2007 to address our recommendation. This study concluded that DOE should continue to pursue developing a supplemental technology to accelerate tank waste cleanup at Hanford but did not endorse bulk vitrification as the best option.
Recommendation: In light of major changes that have occurred on both the bulk vitrification demonstration and the waste treatment plant, which may affect the demonstration's costs, schedule, and mission justification, the Secretary of Energy should direct the Assistant Secretary for Environmental Management to, if a reassessment shows that a supplemental technology is still needed, reassess the relative costs and benefits of demonstrating and deploying bulk vitrification compared with other viable technologies, such as constructing a second low-activity waste vitrification facility.
Agency Affected: Department of Energy
Status: Closed - Implemented
Comments: DOE commissioned an external study of waste treatment plant operations, including supplemental technologies for low-activity waste. This external technical review, which was issued in November 2008, concluded that a bulk vitrification facility was not the best option for meeting the tank waste treatment schedule. In late 2008, on the basis of these reports and the problems encountered with the bulk vitrification demonstration project, DOE decided to cancel the bulk vitrification demonstration project. In March 2009, the assistant manager of DOE's Office of River Protection stated that DOE's tank waste life-cycle cost and schedule baseline, currently being revised, would no longer include a bulk vitrification facility. Consistent with our recommendation, DOE reassessed the need and benefits for bulk vitrification and ultimately decided to cancel the bulk vitrification project.
Recommendation: In light of major changes that have occurred on both the bulk vitrification demonstration and the waste treatment plant, which may affect the demonstration's costs, schedule, and mission justification, the Secretary of Energy should direct the Assistant Secretary for Environmental Management to report to Congress on the results of the reassessment before requesting additional funding for the bulk vitrification project.
Agency Affected: Department of Energy
Explore the full database of GAO's Open Recommendations
»
Mar 1, 2021
-
Man-Made Chemicals and Potential Health Risks:
EPA Has Completed Some Regulatory-Related Actions for PFASGAO-21-37: Published: Jan 27, 2021. Publicly Released: Mar 1, 2021.
Jan 22, 2021
-
U.S. Army Corps of Engineers:
Information on the Navigation and Ecosystem Sustainability ProgramGAO-21-240R: Published: Jan 22, 2021. Publicly Released: Jan 22, 2021.
Jan 19, 2021
-
Chemical Assessments:
Annual EPA Survey Inconsistent with Leading Practices in Program ManagementGAO-21-156: Published: Dec 18, 2020. Publicly Released: Jan 19, 2021.
Jan 15, 2021
-
Environmental Liabilities:
NASA's Reported Financial Liabilities Have Grown, and Several Factors Contribute to Future UncertaintiesGAO-21-205: Published: Jan 15, 2021. Publicly Released: Jan 15, 2021.
Jan 13, 2021
-
Nuclear Waste:
Congressional Action Needed to Clarify a Disposal Option at West Valley Site in New YorkGAO-21-115: Published: Jan 13, 2021. Publicly Released: Jan 13, 2021.
Jan 7, 2021
-
Hanford Cleanup:
DOE's Efforts to Close Tank Farms Would Benefit from Clearer Legal Authorities and CommunicationGAO-21-73: Published: Jan 7, 2021. Publicly Released: Jan 7, 2021.
Dec 18, 2020
-
Drinking Water:
EPA Could Use Available Data to Better Identify Neighborhoods at Risk of Lead ExposureGAO-21-78: Published: Dec 18, 2020. Publicly Released: Dec 18, 2020. -
Recycling:
Building on Existing Federal Efforts Could Help Address Cross-Cutting ChallengesGAO-21-87: Published: Dec 18, 2020. Publicly Released: Dec 18, 2020.
Dec 9, 2020
-
Environmental Protection:
Action Needed to Ensure EPA's Enforcement and Compliance Activities Support Its Strategic GoalsGAO-21-82: Published: Dec 9, 2020. Publicly Released: Dec 9, 2020. -
Oil and Gas:
Onshore Competitive and Noncompetitive Lease RevenuesGAO-21-138: Published: Nov 19, 2020. Publicly Released: Dec 9, 2020.
Looking for more? Browse all our products here