DBI Waste Systems, Inc.
Highlights
DBI Waste Systems, Inc. (DBI), of Everett, Massachusetts, protests the award of a contract to Waste Management, Inc. (WMI) under request for proposals (RFP) No. VA-241-08-0589, issued by the Department of Veterans Affairs (VA) for refuse removal services at Boston-area VA medical facilities. DBI contends that the agency failed to provide adequate notice of the RFP and failed to acknowledge a material amendment to the RFP.
B-400687; B-400687.2, DBI Waste Systems, Inc., January 12, 2009
Decision
Matter of: DBI Waste Systems, Inc.
John M. Curran, Esq., and Michael S. Robertson, Esq., Corwin & Corwin LLP, for the protester.
Edward B. Carney, Department of Veterans Affairs, for the agency.
Frank Maguire, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Protest that agency's publishing of notice of solicitation on government-wide point of entry was inadequate because protester lacks internet access is denied; potential offerors are on constructive notice of solicitation notice published on GPE.
2. Protest that awardee's proposal was ineligible for award because it did not acknowledge solicitation amendment is denied where record establishes that amendment was immaterial; failure to acknowledge immaterial amendment was properly waived by agency.
DECISION
DBI Waste Systems, Inc. (DBI), of
The solicitation, which was for refuse removal at three Boston-area VA facilities, including VA's Jamaica Plain campus, Brockton campus, and West Roxbury campus, was issued on Tuesday, September 23, 2008, and publicized on the government-wide point of entry (GPE), FedBizOpps, at approximately 3 p.m. on that day. AR, exh. 1, Contracting Officer's Statement (COS), at 2. Proposals were due by , Monday, September 29. AR exh. 6. On Friday, September 26, VA amended the solicitation, changing the requirement for a 4 cubic yard compactor under contract line item (CLIN) 09 (
SOLICITATION NOTICE
DBI asserts that the agency should have provided it with individual notice of the RFP, in addition to the notice on FedBizOpps, based on its status as an incumbent and the agency's course of dealing with it in this and in prior acquisitions in which DBI asserts it was orally notified of the solicitation.
This argument is without merit. FedBizOpps has been designated as the GPE, the single point where Government business opportunities greater than $25,000, including synopses of proposed contract actions, solicitations, and associated information, can be accessed electronically by the public. Federal Acquisition Regulation (FAR) sect. 2.101. Protesters are charged with constructive notice of the contents of procurement actions published on the GPE. Herndon & Thompson, B'240748,
DBI's status as an incumbent contractor did not operate to impose some greater notice obligation on the agency. At one time--but no longer--the FAR required that bids shall be solicited from . . . the previously successful bidder or offeror for the requirement. See (superseded) FAR sections 14.205-4 and 15.403. However, the current FAR does not require such notice to incumbent contractors; thus, VA's failure to provide actual notice to DBI provides no valid basis for protest. See PR Newswire Ass'n, LLC, B-400430,
DBI asserts that, on several occasions, its president met with two VA employees, who indicated that they were not sure exactly what was happening, but that VA would let [DBI] know the particulars of the bid once the details were put in place. Comments at 3. However, even as recalled by the protester's president, these vague assurances did not include any specific promise to provide a solicitation other than through legally required means, i.e., FedBizOpps, and, further, the agency advises that the employees in question worked in the agency's Environmental Management Service, not the contracting office.
FAILURE TO PUBLICIZE FOR 30 DAYS
DBI asserts that the agency improperly failed to publicize the solicitation for 30 days, as it claims is required under the FAR. Under our Bid Protest Regulations, protests of alleged RFP improprieties must be filed no later than the closing time for initial proposals. 4 C.F.R. sect. 21.2(a)(1) (2008). Here, the RFP as published on FedBizOpps specifically provided that proposals were due by September 29. Thus, any argument that this due date was inconsistent with the 30-day requirement had to be raised prior to that date. DBI's protest was not filed in our Office until after award; accordingly, it is untimely and will not be considered. We point out that, while, as already discussed, DBI allegedly did not view the RFP prior to the closing time, this fact has no bearing on our conclusion; again, DBI was on constructive notice of the RFP and its contents by virtue of its posting on FedBizOpps.
AWARDEE'S FAILURE TO ACKNOWLEDGE AMENDMENT
As indicated above, on September 26, VA amended CLIN 09 of the RFP, changing the phrase 4 CU YD compactor to 4 CY CONTAINER. AR exh. 2 at 1. DBI maintains that the record shows that
We find the waiver unobjectionable. In determining whether an amendment is material, we look at the facts of each case. While no precise rule exists as to whether a change required by an amendment is more than negligible, such that failure to acknowledge the amendment renders the proposal unacceptable, an amendment is material where it imposes legal obligations on a party that are different from those contained in the original solicitation, or if it would have more than a negligible impact on price, quantity, quality, or delivery. See Skyline ULTD, Inc., B-297800.3,
DBI asserts that the amendment was material because a compactor, including its wiring and installation, is far more expensive than a mere container. Comments at 12. However, it appears from the record that there is no effective price difference between the two items. VA reports that all of the offerors submitted the same price for the compactor and the container CLINs,
The protest is denied.
Gary L. Kepplinger
General Counsel