Sea Box, Inc.

B-291056: Oct 31, 2002

Sea Box, Inc. protests the rejection of its proposal as late under request for proposals (RFP) No. DAAE07-02-R-S104, issued by the U.S. Army Material Command (AMC) for a quantity of container roll-in/out platforms.We deny the protest...

  • pdf icon View Decision (PDF, 3 pages)
  • html report icon View Decision (HTML)
Sea Box, Inc., B-291056, October 31, 2002

B-291056: Oct 31, 2002

DIGEST Protest that agency improperly rejected proposal as late is denied where proposal was submitted electronically. Was not received at the initial point of entry to the government infrastructure by 5:00 p.m. 1 working day prior to the deadline for submitting proposals. The exception that permits consideration of late proposals that are received at the government installation. Is inapplicable t...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap