L-3 Communications Corporation, Ocean Systems Division--Costs

B-281784.5: Feb 17, 2004

L-3 Communications Corporation, Ocean Systems Division, requests that we recommend the amount it should be reimbursed by the Department of the Navy for filing and pursuing its protest in L3 Communications Corp., Ocean Sys. Div. B-28209;281784.3, B-281784.4, Apr. 26, 1999, 99-1 CPD 6 81.We deny the request...

  • pdf icon View Decision (PDF, 4 pages)
  • html report icon View Decision (HTML)
L-3 Communications Corporation, Ocean Systems Division--Costs, B-281784.5, February 17, 2004

B-281784.5: Feb 17, 2004

DIGEST Request for recommendation for reimbursement of protest costs is denied for failure to diligently pursue claim where protester failed to contact agency for nearly 3 years regarding resolution of previously filed claim and. The protester was directed to submit to the contracting agency. The Navy reported to L-3 that an audit of the claim revealed that the vast majority of the costs were unre...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap