B-278076.2:
Jan 20, 1998
A firm protested an Army Corps of Engineers contract award for landscaping and signage services, contending that the: (1) Army should have rejected the awardee's bid as nonresponsive because it failed to acknowledge a solicitation amendment; and (2) amendment was material because it clarified two solicitation ambiguities. GAO held that the Corps properly waived the awardee's failure to acknowledge...