B-274766:
Jan 2, 1997
A firm protested the Army Corps of Engineers' rejection of its low bid and contract award for floating bulkheads and pier extension construction, contending that the Corps: (1) unreasonably determined that its alternate design proposal was technically unacceptable; and (2) improperly made award on the basis of initial bids. GAO held that: (1) the Corps reasonably rejected the protester's low bid,...