B-274052:
Aug 13, 1996
A firm protested the Department of Energy's rejection of its bid for paging services, contending that no firm was capable of providing the level of service required. GAO held that the protester: (1) untimely filed its protest more than 10 days after it knew the basis of protest; and (2) should have raised its concerns about the service requirement before bid opening. Accordingly, the protest was d...