B-271034.2:
Nov 20, 1997
A firm requested reimbursement for the costs of its sustained protest under an Army Corps of Engineers solicitation, contending that it should be reimbursed: (1) the full amount of its costs in pursuing the protest, not only the costs for issues sustained by GAO; and (2) for components of the cost claim such as legal fees, and hours claimed by employees and subcontractors. GAO held that the protes...