Skip to main content

[Protest of ARS Contract Award for Operations and Maintenance Support Services]

B-270648 Published: Jan 24, 1996. Publicly Released: Jan 24, 1996.
Jump To:
Skip to Highlights

Highlights

A firm protested an Agricultural Research Service (ARS) contract award for operations and maintenance support services, contending that: (1) ARS improperly evaluated the awardee's proposed personnel; (2) ARS made an improper cost/realism and best value determination; and (3) the awardee had an organizational conflict of interest. GAO held that the protester was not sufficiently interested to protest the award, since it would not be in line for award even if its protest were sustained. Accordingly, the protest was dismissed.

Full Report

Office of Public Affairs