B-265793:
Dec 29, 1995
A firm protested an Environmental Protection Agency (EPA) contract award for energy pressure vessels, contending that EPA: (1) failed to conduct meaningful discussions; (2) improperly evaluated its technical proposal using an undisclosed evaluation criterion; and (3) made an unreasonable cost-technical tradeoff decision when it selected the awardee's technically superior high bid. GAO held that EP...