[Protest of Navy Contract Award for Kitchen and Bathroom Remodeling]
B-262115
Published: Nov 28, 1995. Publicly Released: Nov 28, 1995.
Skip to Highlights
Highlights
A firm protested a Navy contract award for kitchen and bathroom remodeling, contending that the Navy improperly: (1) cancelled the solicitation and resolicited its requirements; and (2) allowed the awardee to correct a mistake in its initial bid. GAO held that the protester: (1) failed to provide sufficient evidence that the awardee corrected an alleged error in its initial bid; and (2) untimely filed its protest more than 10 days after it knew the basis of protest. Accordingly, the protest was dismissed.