Skip to main content

[Protest of Navy Contract Award]

B-260754 Published: Mar 28, 1995. Publicly Released: Mar 28, 1995.
Jump To:
Skip to Highlights

Highlights

A firm protested a Navy contract award, contending that the Navy restricted competition by not defining quantities under certain contract line items until after the bidders priced all other items. GAO held that: (1) the protester untimely filed after bid opening its protest of alleged solicitation improprieties; and (2) it would not consider untimely bid protests. Accordingly, the protest was dismissed.

Full Report

Office of Public Affairs