[Protest of GSA Bid Rejection]

B-260193: Feb 3, 1995

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the General Services Administration's (GSA) rejection of its bid, contending that: (1) GSA improperly rejected its bid for failure to specify the minimum bid acceptance period; and (2) its bid error could be corrected after bid opening. GAO held that: (1) GSA properly rejected the protester's bid, since it failed to comply with a material solicitation requirement; and (2) the requirement could not be waived or corrected after bid opening. Accordingly, the protest was dismissed.

Oct 19, 2018

Oct 17, 2018

Oct 16, 2018

Oct 15, 2018

Looking for more? Browse all our products here