[Request for Protest Costs Pursuant to Protests of DOE Rejection of Bids for Technical Support Services]

B-259681.3: Oct 12, 1995

Additional Materials:


Office of Public Affairs
(202) 512-4800

A firm requested reimbursement of its protest costs pursuant to its protests of a Department of Energy (DOE) prime contractor's rejection of its bids for technical support services. GAO held that the protester was not entitled to reimbursement of its protest costs, since: (1) DOE cancelled the unrestricted solicitation in response to the protests; and (2) the protester's failure to provide DOE with copies of its protests contributed to the delay in corrective action. Accordingly, the claim for protest costs was denied.

Mar 15, 2018

  • ORBIS Sibro, Inc.
    We sustain the protest in part and deny it in part.