[Protest of HUD Contract Award]

B-259644.2 Published: Dec 28, 1994. Publicly Released: Dec 28, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested a Department of Housing and Urban Development (HUD) contract award, contending that the awardee was not responsible. GAO held that the protester: (1) failed to provide any evidence that HUD acted in bad faith or misapplied definitive responsibility criteria; and (2) untimely filed its agency-level protest more than 10 days after it knew the basis of protest. Accordingly, the protest was dismissed.