[Protest of Army Corps of Engineers Contract Termination and Subsequent Contract Award]

B-259573: Apr 13, 1995

A firm protested the Army Corps of Engineers' cancellation of its contract for facility construction and its subsequent contract award to another bidder, contending that: (1) the Corps improperly terminated its contract for convenience; (2) the Corps properly permitted it to correct its mathematical bid errors; (3) its bid price was not ambiguous; and (4) the awardee's bid was nonresponsive. GAO h...

  • pdf icon View Decision (PDF, 7 pages)
Matter: Metric Construction Co., Inc. File: B-259573 Date: April 13, 1995

B-259573: Apr 13, 1995

Agency reasonably found that bid correction was improper where bid contained numerous discrepancies such that the bid was susceptible to several reasonable interpretations. Create a presumption that only one of several reasonable interpretations is necessarily correct. Where bid contains numerous and varied errors which make it impossible to determine which prices were intended. Specified portions...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap