B-258498,B-258508 Published: Nov 08, 1994. Publicly Released: Nov 08, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested the Navy's rejection of its bids as nonresponsive, contending that the: (1) Navy's rejection was improper, since the defects in its bid bonds could be cured after bid opening; and (2) bond requirements were confusing and contradictory. GAO held that the: (1) Navy properly rejected the protester's bids as nonresponsive, since its bid bonds were not in the proper amounts; and (2) protester untimely filed after bid opening its protests of the solicitations' bond requirements. Accordingly, the protests were dismissed.

Office of Public Affairs

Topics

Bid bondsBid guaranteesBid rejection protestsBid responsivenessDefective solicitationsNaval procurementUntimely protestsU.S. NavyProtests