[Request for Reconsideration of Protest of Customs Service Contract Award]

B-258293.3: Aug 24, 1995

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm requested reconsideration of its denied protest of a Customs Service contract award. In its request for reconsideration, the protester contended that the Customs Service improperly rejected its bid as technically unacceptable. GAO held that the: (1) Customs Service reasonably rejected the protester's bid as technically unacceptable, since the protester failed to demonstrate its capability of performing the work; and (2) protester failed to show any legal or factual errors that would warrant reversal or modification of the original decision. Accordingly, the request for reconsideration was denied.

Apr 26, 2018

Apr 25, 2018

Apr 24, 2018

Apr 23, 2018

Apr 20, 2018

Looking for more? Browse all our products here