[Protest of Navy Contract Award]

B-256887 Published: Apr 20, 1994. Publicly Released: Apr 20, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested a Navy contract award, contending that it timely filed its protest after it received all requested information on the awardee. GAO held that the protester: (1) untimely filed its protest more than 10 days after it knew the basis of protest; and (2) received sufficient oral information to form its basis of protest. Accordingly, the protest was dismissed.