The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Request for Reconsideration of Protest of Army Corps of Engineers Contract Award]

B-256556.2: Dec 12, 1994

A firm requested reconsideration of its denied protest of an Army Corps of Engineers contract award for runway replacement and lighting. GAO had held that the Corps: (1) properly awarded the contract to the bidder with the lowest evaluated cost; and (2) reasonably determined that the awardee could successfully perform the contract within its proposed performance period. In its request for reconsid...

  • pdf icon View Decision (PDF, 4 pages)
Matter of: Cedar Valley Corp.--Reconsideration File: B-256556.2 Date: December 12, 1994

B-256556.2: Dec 12, 1994

Request for reconsideration of decision denying protest is denied where the protester does not show that the decision contained any errors of fact or law or present information not previously considered that warrants reversal or modification. Were added to the bidders' prices. Bidders were informed of the dates the contractor would have access to the runway. The evaluated cost total for each bid s...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap