[Protest of FAA Contract Award for Office Space]

B-253339.6: Mar 25, 1994

Additional Materials:


Office of Public Affairs
(202) 512-4800

A firm protested a Federal Aviation Administration (FAA) contract award for office space, contending that: (1) FAA did not evaluate the bids in accordance with the solicitation's evaluation criteria; and (2) the awardee was ineligible to receive award. GAO held that it would not consider the protest, since the protest was pending before a court of competent jurisdiction. Accordingly, the protest was dismissed.

Mar 15, 2018

  • ORBIS Sibro, Inc.
    We sustain the protest in part and deny it in part.