B-250092:
Sep 23, 1992
A firm protested the General Services Administration's (GSA) rejection of its bid for retrofit lighting, contending that GSA improperly determined that its bid bond was defective. GAO held that GSA properly determined that the bid was nonresponsive. Accordingly, the protest was dismissed...