[Protest of Interior Contract Modification]

B-245293: Dec 23, 1991

A firm protested the Department of the Interior's modification of a contract for minicomputer systems and software, contending that the modification constituted a cardinal change that exceeded the original contract's scope. GAO held that: (1) Interior reasonably encouraged and evaluated all bidders' offers of optional equipment; and (2) there was no material difference between the modified contrac...

  • pdf icon View Decision (PDF, 5 pages)
B-245293, Dec 23, 1991

B-245293: Dec 23, 1991

DIGEST: Contract modification resulting from an engineering change proposal to provide a significantly less expensive and more powerful UNIX operating system was not outside the scope of the contract where the original solicitation requested offerors to propose a UNIX operating system which was evaluated and included as part of the original contract. The computer systems were to be installed at va...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap