B-243855.2, Jul 10, 1991, 91-2 CPD ***

B-243855.2 Jul 10, 1991
Jump To:
Skip to Highlights

Highlights

PROCUREMENT - Bid Protests - GAO procedures - GAO decisions - Reconsideration DIGEST: Request for reconsideration of prior decision is denied where protest of specifications accompanying proposal does not constitute timely protest of alleged solicitation improprieties. We dismissed the protest as untimely because it was not filed prior to the closing date for the receipt of proposals. Contending it was unduly restrictive. Our Bid Protest Regulations provide that protests based upon alleged improprieties in a solicitation which are apparent prior to the closing date for receipt of proposals must be filed prior to that date. 4 C.F.R. Our Office does not consider a protest submitted in a proposal as timely because the contracting agency is under no obligation to open or read proposals until after the closing date and.

View Decision

B-243855.2, Jul 10, 1991, 91-2 CPD ***

PROCUREMENT - Bid Protests - GAO procedures - GAO decisions - Reconsideration DIGEST: Request for reconsideration of prior decision is denied where protest of specifications accompanying proposal does not constitute timely protest of alleged solicitation improprieties.

Attorneys

Panasonic Communications & Systems, Co.-- Reconsideration:

Panasonic Communications & Systems Co. requests reconsideration of our May 13, 1991, dismissal of its protest challenging the terms of request for proposals No. DAACO9-91-R-0012, issued by the Department of the Army for video equipment. We dismissed the protest as untimely because it was not filed prior to the closing date for the receipt of proposals.

We affirm the dismissal.

Panasonic enclosed with its initial proposal, due March 11, 1991, to the Army a cover letter dated March 8, in which it objected to the agency's requirement for the equipment to be Betacam and Betacam SP format, contending it was unduly restrictive. Panasonic received notification of the Army's denial of its protest on April 16. Panasonic then filed a protest with our Office on April 30, 1991.

Our Bid Protest Regulations provide that protests based upon alleged improprieties in a solicitation which are apparent prior to the closing date for receipt of proposals must be filed prior to that date. 4 C.F.R. Sec. 21.2(a)(1) (1991); Allen Organ Co., B-231473, June 9, 1988, 88-1 CPD Para. 552. Thus, Panasonic's protest of the solicitation requirements as unduly restrictive had to be filed prior to the closing date. Here, Panasonic filed its protest with its proposal. Our Office does not consider a protest submitted in a proposal as timely because the contracting agency is under no obligation to open or read proposals until after the closing date and, therefore, has no notice prior to closing of a solicitation impropriety alleged in such a protest. Paramount Sys., Inc., B-229648.2, Dec. 30, 1987, 87-2 CPD Para. 646.

Where, as here, a protest is filed initially with the contracting agency, our Office will consider a subsequent protest only if the initial protest was timely filed, and the subsequent protest is filed within 10 working days of actual or constructive knowledge of initial adverse agency action. 4 C.F.R. Sec. 21.2(a)(3). Since the protest to the agency was not timely filed, we dismissed the subsequent protest to our Office.

On reconsideration, Panasonic argues that if its protest were untimely, it falls under the good cause and significant issue exceptions found in our Bid Protest Regulations. 4 C.F.R. Sec. 21.2(c). The good cause exception is limited to circumstances where some compelling reason beyond the control of the protester prevents the protester from submitting a timely protest. Commercial Energies, Inc., B-242261.2, Mar. 21, 1991, 91-1 CPD Para. 312. Panasonic's decision to submit its protest with its proposal was well within its control. In addition, our Office will not consider the merits of an untimely protest by invoking the significant issue exception, where the protest does not raise an issue of first impression or one that would be of widespread interest to the procurement community. Keco Indus., B-238301, May 21, 1990, 90-1 CPD Para. 490. The issue of unduly restrictive specifications has been addressed by our Office on numerous occasions. See, e.g., AUTOFLEX, Inc., B-240012, Oct. 16, 1990, 90-2 CPD Para. 294; DBA Sys., Inc., B-237596, Feb. 23, 1990, 90-1 CPD Para. 214. While we recognize the importance of the matter to the protester, we do not think the specific issue raised in this protest is of widespread interest to the procurement community. Accordingly, we will not invoke the good cause or the significant issue exceptions here.

Panasonic also contends that the dismissal was improper because we dismissed the protest without giving Panasonic an opportunity to respond to the Army's May 10 request for summary dismissal. Our dismissal of Panasonic's protest was based on information provided by the Army that clearly showed Panasonic's agency-level protest was not timely filed.

Our Bid Protest Regulations provide that we may dismiss a protest at the time the propriety of a dismissal becomes clear based upon information provided by the contracting agency. 4 C.F.R. Sec. 21.3(m). Consequently, our dismissal of Panasonic's protest prior to receipt of Panasonic's comments was proper. See AOI Sys., Inc.-- Recon., B-240768.2, Oct. 16, 1990, 90-2 CPD Para. 300. Since the protester has presented no information establishing that our prior dismissal of the protest was erroneous, the request for reconsideration is denied.

GAO Contacts