B-233009:
Oct 25, 1988
A firm protested the General Services Administration's (GSA) rejection of its bid for elevator modernization, contending that substitution of its original unacceptable sureties did not render its bid nonresponsive. GAO held that GSA properly rejected the protester's bid, since the substitution of its unacceptable sureties would have altered the sureties' liabilities under the bid bond. Accordingly...