B-232553:
Sep 28, 1988
A firm protested an Army contract award for housing assemblies, contending that the Army: (1) improperly failed to determine the awardee's capability to meet its proposed delivery schedule; and (2) should have included offerers' ability to meet the delivery schedule as a technical evaluation factor. GAO would not review the Army's affirmative determination of the awardee's responsibility, absent e...