B-232421:
Nov 28, 1988
A firm protested a Navy contract award for turbine blade sets, contending that the Navy unreasonably determined that it could not timely meet its urgent delivery requirements. GAO held that the Navy was not required to rely on the protester's estimate of the lead time it required for source approval and first-article testing and production. Accordingly, the protest was denied...