B-232416:
Sep 29, 1988
A firm protested the Army Corps of Engineers' rejection of its bid for failure to provide an adequate bid guarantee, contending that the Army should have accepted the letter of credit it submitted with the additional guarantees it offered. GAO held that the Army properly rejected the bid, since the surety: (1) was under investigation for misrepresenting its financial condition; and (2) had virtual...