The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Request for Reconsideration of Denied Protest of Air Force Contract Award]

B-232131.2: Dec 1, 1988

A firm requested reconsideration of its denied protest of an Air Force contract award for oscillograph strip-chart recorders. GAO had held that the awardee's equipment complied with the solicitation requirements. In its request for reconsideration, the protester contended that: (1) the awardee's equipment did not meet the solicitation channel-range requirements; and (2) GAO should hold a conferenc...

  • pdf icon View Decision (PDF, 3 pages)
B-232131.2, Dec 1, 1988, 88-2 CPD 545

B-232131.2: Dec 1, 1988

PROCUREMENT - Bid Protests - GAO procedures - GAO decisions - Reconsideration DIGEST: General Accounting Office will not hear on reconsideration an argument which the protester could have raised. Astro-Med cited the principal deficiency of the Mark 10 as failure to meet the channel range requirement that "the waveform ... have the ability to exceed both edges of the grid by 4 millimeters to facili...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap