B-230143:
Feb 12, 1988
A firm protested the Army's rejection of its late bid, contending that, in a telephone conversation, Army representatives agreed to accept its bid at the visitor control center rather than at the designated procurement office. GAO held that the Army properly rejected the bid as late, since: (1) the protester was responsible for delivering the bid to the proper place at the proper time; (2) there w...