B-230103.2:
Oct 24, 1988
A firm requested reconsideration of its denied protest against the Defense Logistics Agency's (DLA) termination of a contract and subsequent resolicitation of the requirement. GAO had held that DLA properly terminated its contract with the protester and resolicited the requirement, since the: (1) initial solicitation understated the agency's actual needs; and (2) protester's bid was mathematically...