[Protest of Army Procurement Procedures]

B-229675: Jan 26, 1988

A firm protested that the Army: (1) had repeatedly refused to solicit it for a cleaning compound; and (2) improperly denied it the opportunity to compete under prior solicitations for the compound. GAO held that the protester: (1) failed to protest under a specific procurement; and (2) untimely protested the alleged prior solicitations. Accordingly, the protest was dismissed...

  • pdf icon View Decision (PDF, 1 pages)
B-229675, Jan 26, 1988, 88-1 CPD 79

B-229675: Jan 26, 1988

PROCUREMENT - Bid Protests - GAO Procedures - Protest Timeliness - 10 day Rule DIGEST: Protest that firm was unreasonably denied an opportunity to compete filed months after procurements were conducted is untimely filed since the General Accounting Office Bid Protest Regulations require that a protest be filed no later than 10 working days after the basis of protest is known or should have been kn...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap